Materials Requirement Planning (MRP) The objective of MRP is to ensure material availability for the requirements. Requirements could be of two types – internal requirements and external requirements. External requirements originate from customer requirements which are entered into SAP as a sales order (for example). Internal requirements are to manufacture components on the same plant which could be supplied as components to finished goods or to satisfy the customer requirements. SAP MRP checks the stock level of the respective material and generates procurement proposals or planned orders which could be either converted to purchase requisitions or production orders based on the MRP settings in material master records. Master Data for MRP The following master data is required to carry out SAP MRP process: 

Material master



Bills of material



Work center (in-house production)



Routings (in-house production)



Demand management



Sales and distribution (if required)

For SAP MRP process to be carried out, material master would need to be maintained accordingly. Material master has several views related to MRP viz. MRP1 to MRP4. MRP 1 view has fields like purchasing group, plant special material status, MRP procedure, and lot size data.

SAP Material Master – MRP 1 View

SAP Material Master – MRP 2 View In material master MRP 2 view, fields like procurement type, special procurement, scheduling margin key, and planned delivery time are located. There is a separate tab available for net requirements calculation which includes safety stock, minimum safety stock which helps to calculate the required quantity at the right time.

SAP Material Master – MRP 3 View Material master MRP 3 view includes fields like strategy group which is used to decide between Make-To-Order (MTO) or Make-To-Stock (MTS) scenarios. Also, Availability check filed is available which is used to maintain the checking rule for checking the material availability and update it for available to promise dates and quantities.

SAP Material Master – MRP 4 View In material master MRP 4 view, fields for BOM explosion and dependent requirements are available. There is a separate tab available for Repetitive Manufacturing which helps to maintain REM profile that is used to enter and record transactions for repetitive manufacturing. If a material is subject is to in-house production, then work scheduling view would need to be maintained. If a material is subject to MRP planning, then all the four views of MRP would need to be maintained in material master. SAP MRP Process Flow SAP MRP process flow starts with customer requirement, which originates from the sales department or marketing department. The customer requirements are entered in SAP via sales orders. The customer requirements are entered as demand in demand management system. The output of demand management is Planned Independent Requirements which would be used in long-term planning. Now, materials requirement planning comes into picture. The input to MRP is from sales order and planned independent requirement, if applicable. When the MRP run is carried out, planned order or purchase requisition would be generated based on the planning run settings. Planned order could be converted into purchase requisition (PR) or Production order. Purchase requisition is for external procurement and production order is for in-house production. SAP will then convert all the dependent requirements of planned order into reservations in the production order. When planned order is created for external procurement, it would need to be reviewed by planners, and if required planners would convert the planned order to purchase requisition. Otherwise, the purchase requisition would be generated automatically and available for purchasing. In SAP MRP process, the system calculates the net requirements while considering available warehouse stock and scheduled receipts from purchasing and production. During MRP process all levels of the bill of material are planned.

SAP MRP Process Overview SAP MRP Planning run can be executed at plant level or MRP area level. This planning run can be executed for a single material or a material group. Planning run can be total planning for a plant, single-item single level planning, or multi-level single item planning. The SAP system

creates procurement proposals which could be planned orders, purchase requisitions, schedule lines based on the planning run settings. Planning file entry contains details of the materials that are to be included for the MRP run. SAP MRP Planning run type depends on the processing key in the MRP run screen. There are three types of processing key: 

NETCH – Net change planning in total horizon.



NETPL – Net change planning in the planning horizon.



NEUPL – Regenerative planning.

SAP MRP Planning Run

SAP MRP Planning Run Initial Screen The figure above shows planning run at material level. The material and a respective plant are entered.

There are several fields which come under MRP control parameters control data. 

Processing key field – net change in the planning horizon.



Create Purchase Requisition – This field has an option for creating purchase requisitions or planned orders.



Scheduling Agreement (SA) delivery schedule lines – This field has an option for creating schedule lines / no schedule lines. To create a scheduling agreement there should be settings maintained in a source list.



Create MRP list – MRP list would be created and displayed when the planning run is executed and saved.



Planning mode – In this field, the planning mode would be maintained whether to run normally or delete and create all planning data or re-explode BOM and routing, if there are any changes made to those master data.

Transactions for SAP MRP Planning Run Transaction code: MD01 SAP Menu -> Logistics-> Production-> MRP -> Planning -> Total Planning -> Online With this transaction code, we would be able to carry out planning run at a plant level. As this would consume a lot of time for the output to be displayed, it could be executed as a background job.

Transaction MD01 – Planning Run at Plant Level

Transaction Codes for Planning Run MD02 – This transaction code is used to execute a planning run for a material and used to explode multi-level materials.

SAP MRP Planning Run for Single-Item, Multi-Level

SAP MRP Planning Run for Single-Item, Single-Level In this planning run, MRP would be carried for a material and for the first level of BOM, the other components will not be included for planning.

Stock/Requirement List – Transaction MD04 In the transaction code MD04, we could get the latest stock / requirement list for a particular material and plant wise. Enter the material and plant; this would give you the current stock with requirements or receipts.

Stock / Requirement List for a Material